This case has been cited 1 times or more.
2015-11-10 |
PERLAS-BERNABE, J. |
||||
(a) On September 21, 2010, Binay, Jr. issued the Notice of Award[21] for Phase III of the Makati Parking Building project to Hilmarc's Construction Corporation (Hilmarc's), and consequently, executed the corresponding contract[22] on September 28, 2010,[23] without the required publication and the lack of architectural design,[24] and approved the release of funds therefor in the following amounts as follows: (1) P130,518,394.80 on December 15, 2010;[25] (2) P134,470,659.64 on January 19, 2011;[26] (3) P92,775,202.[27] on February 25, 2011;[27] (4) P57,148,625.51 on March 28, 2011;[28] (5) P40,908,750.61 on May 3, 2011;[29] and (6) P106,672,761.90 on July 7, 2011;[30] |